NEW

How to make change management happen in the most effective way

Many things can put your business at risk, including changes to your organisation, people or technology. The current pandemic has put many businesses under unprecedented pressure, and some even teetering on the brink of survival. Crises like this quickly turn change...

Future-ready part 2: Diversity – an essential ingredient for a future-ready organisation

In his seminal 1937 essay, “The nature of the firm,” the economist and eventual Nobel laureate Ronald Coase argued that corporations exist to avoid the transaction costs of the free market. Yet with transaction costs plummeting (spurred by rising connectivity)...

Future-ready part 1: What does a future-ready business look like in the new normal?

The pressure to change had been building for years. Well before the COVID-19 pandemic, senior executives routinely worried that their organisations were too slow, too siloed, too bogged down in complicated matrix structures, too bureaucratic. What many leaders feared,...

Organisation Design: Restructuring or Reshuffling to enable Strategy

Customer expectations are not just changing; they are exceeding the ability of a business to deliver on time. They are looking for alternatives, with more emphasis on experience and convenience. To keep up, companies are evolving their offering to meet the...

How to fill the gap between Strategy and Execution

Organisations are great at setting their strategy and identifying their goals, but they fall short when it comes to their operating model review and redesign, the key component that enables the strategy and drives the achievement of goals. Operating models consist of...

Culture PART 2: The role of leaders in a culture shift

In the previous article in this series we examined the effect of COVID-19 on an organisation’s culture. Now, we turn the focus onto the role of leadership and technology in leveraging culture. When an organisation decides to change its culture – be it planned or...

Culture PART 1: Did COVID-19 signal the end for hierarchical organisations?

According to the Organisation for Economic Co-operation and Development, human capital is defined as: “the knowledge, skills, competencies and other attributes embodied in individuals or groups of individuals acquired during their life and used to produce goods,...

Meet MAC’s Executives: Karina Jardim, Senior Executive

“Exceptionally talented consultant” “An absolute pleasure to work with” “Driven by a desire to see people grow” If you know Karina Jardim, you know that these phrases used to describe Karina ring undoubtedly true. She is a name that is valued to every MACer, whether...

Thriving in the Age of Digital Adoption: Embracing the Workforce Ecosystem (part 2)

In the first part of this series, we looked at how the fears of technological innovation are resulting in an unproductive resistance toward modernisation, even as it gains extraordinary pace in 2021. We also delved into the importance of a growth mindset in allowing...

Thriving in the Age of Digital Adoption: Overcoming the Fear of AI (part 1)

“What if artificial intelligence takes over my job? What if I become redundant?” Every one of us has experienced technology encroaching on our lives, more and more so with each year that passes. It appears that technological innovation is a certainty that is only...



Mac Consulting

Business Case Analysis -  What a Project Manager should know: Part 3

Mac Minds Insights | Mac Consulting

Business Case Analysis - 
What a Project Manager should know: Part 3

In part 2 of this article we looked at the various components of the Business Case that should be considered. In this part we dive into the various aspects of Business Case costing, and highlight important considerations.

When is a savings not a savings: Cost transfers and cost avoidance or “there ain’t no such thing as a free lunch”(tanstaafl)

Every project manager should have the word tanstaafl pinned to the wall in front of them as they are preparing their business case as a reminder that if a cost is not completely eliminated it goes somewhere. The following are three brief examples of cost transfers. Several years ago, the rage in manufacturing was a concept called “Just in time” (J.I.T). It was a great cost cutting measure because a company significantly reduced its inventory and carrying costs — by transferring these costs to their suppliers. With J.I.T. a true cost reduction for all parties couldn’t be obtained until a firm instituted such things as EDI (Electronic Data Interchange), automated billings and piggybacked deliveries, which they many of them ultimately had to do to keep their vendors from raising prices to cover the costs the company shifted over to them.

A second example of a cost transfer is one seen frequently on proposals to convert from an existing mainframe system to a user supported client server system. The allocated cost of the mainframe system often serves as the only cost savings on the proposal without taking into account that unless the system being replaced will allow for the elimination of the mainframe and its support staff, mainframe operating costs will remain the same and will simply be reallocated to the other systems remaining on the mainframe. The overall impact of this system proposal is a net cost increase for the company.

The third example goes back to the earlier scenario of eliminating accounts payable by allowing receiving to authorise payment. Some portion of those costs were not really saved because the work simply moved from a centralised location to a decentralised location. When this happens, it may not be noticeable since the incremental additional work may be absorbed by displacing some lower priority assignment. Also based on actually seeing this concept implemented at a client, it is also very unclear how much work moved from an accounts payable clerk being paid a clerical wage to mid-level manager. The cost per unit of activity in most cases would have risen on a full cost basis but since management overtime is free, there was a direct savings to the bottom line.

Rule of Thumb: Make sure your system completely eliminates a cost and does not just transfer it. If a cost transfer is unavoidable make sure to include these cost as ongoing costs of the new system.

Cost Avoidance – On the scale of possible justifications for a system, cost avoidance is generally considered the weakest. The thought process appears to be that since the company is currently not incurring any of these costs it’s impossible to say they really will incur them in the future. The key to using cost avoidance as a justification is to do the right job quantifying the factors that would drive the increase in current cost. A system proposed in response to an impending regulatory change that would require increased record keeping would be an example of cost avoidance but in this instance, there is a clearly defined outside factor that is driving the increase in cost.

Rule of Thumb: Turn cost avoidance into cost savings where ever possible. If it isn’t possible make sure that there is a clearly definable cause driving the cost increase.

One time project costs

This is usually the most critical component of the business case for the project manager because it’s the most measurable. In fact at one Fortune 100 company the project managers have just been informed that their performance reviews will be based on their ability to stay within the financial targets defined in the business case for their project.

One-time costs may include the following major categories:

Period Expense- Development

  • personnel costs (both internal and external personnel) for the life cycle of the project. Cost components for these charges consist of salaries and direct non-wage (training, supplies, travel, etc.). It also consists of benefits and square meterage charges for facilities.
  • operating costs during system development, including computer processing time, network charges, space allocations, and lease or rental of specific equipment used in system design or development

Period Expense — Implementation

  • start-up costs, such as disruption of business processes due to the conversion to the new system or new business processes; extra work hours required to compensate for lower productivity in the start-up phase. These expenses should be estimated to determine total project cost for the business case. In reality they are virtually impossible to track and should not be included in the projects operating budget.
  • Restructuring Expense costs of reorganization toward the new business processes: job redesigns, hiring or reassigning people, developing new policies, developing and deploying new systems.
  • start-up training or retraining costs.

Capital

  • acquisition costs of package software including software, installation services, vendor training and support upgrades to other software components and documentation
  • acquisition costs for equipment, including all hardware, software, operating systems, etc. that will become part of the system or that will be used to support the system development or training (for example, equipment for computing, data storage, communication, printing, scanning or sensing)

The meaning of period expenses and capital expenses should be fairly clear cut. Restructuring expenses though are a hybrid category that has become much more common recently. When a company is facing a major disruptive reorganisation that they feel will negatively impact operational performance for some period of time in the future (usually two to three years), they will often opt to establish a restructuring reserve by taking a onetime write-off to the income statement. This will give them an immediate tax advantage and will eliminate the long-term damage to the share price that several years of substandard operating profits would entail. The existence of such a reserve does not directly affect the overall cost shown in the business case, but it may have a strong impact on the makeup of individual cost components.

Rule of Thumb : If your company has a restructure reserve make sure you know the rules and comply with them. Actual project cost might be somewhat higher than under alternate sources of funding (often contract labour is eligible for reserve funding while employee labour is not) — but your odds of getting funding are tremendously higher.

In part 4 of this article we look relevant metrics and indicators of a Business Case.

Rules of Thumb Source: Donna Fitzgerald (Donna Fitgerald internet presentation)